Data Center Energization Readiness Checklist
What to confirm before energizing medium- and low-voltage equipment. Use it at the pre-energization meeting and keep a signed copy with the turnover record.
1. Documentation
- Current issued-for-construction one-line diagram on site and matching the field
- Energization sequence written, reviewed and approved by the GC, CxA and owner
- Short-circuit, coordination and arc flash studies complete, with settings issued
- Approved submittals and OEM installation instructions on file for each piece of equipment
- Authority having jurisdiction (AHJ) inspections passed where required
2. Installation complete
- Equipment set, anchored and leveled per drawings and OEM requirements
- Terminations complete and torqued to specification, with torque marks applied
- Grounding and bonding installed and verified
- Covers, barriers and doors installed; equipment cleaned and free of debris and tools
- Arc flash and equipment labels installed
- Open construction issues affecting this equipment closed or formally accepted
3. Testing complete
- Acceptance testing complete (for example, NETA ATS) with results reviewed
- Insulation resistance, contact resistance and phasing checks passed
- Protective relay settings applied and functionally tested
- OEM startup prerequisites met and the OEM field engineer scheduled if required
- Upstream source energized, tested and stable
4. Safety
- Pre-startup safety review completed and signed
- Lockout/tagout procedure written for the energization boundary, with locks and tags placed
- Energized electrical work permits issued where required
- Qualified persons identified, with PPE suitable for the arc flash rating
- Fire alarm and life safety systems operational in the affected area
- Area barricaded and signage posted
5. Communication
- Energization notice issued to all trades with date, time and boundary
- One person named with authority to give the final GO
- Roles assigned for switching, verification and monitoring
- Stop-work and emergency procedures briefed to everyone involved
6. After energization
- Voltage and phase rotation verified at the equipment
- Infrared scan scheduled once the equipment is under load
- Energized status communicated and drawings, signage and LOTO boundaries updated
- Results and sign-offs filed in the project record
This checklist is a general guide. Always follow the approved project documents, OEM requirements, NFPA 70E, applicable codes and your site safety program. Also see the free Commissioning Checklist: L1 FAT to L5 IST.