What to confirm at each commissioning level, from preconstruction to owner acceptance. Use it to plan the commissioning scope and check progress at each level.
Precon: planning and design review
- Owner's project requirements (OPR) and basis of design (BOD) reviewed by the commissioning authority
- Commissioning plan issued, with roles for the owner, GC, CxA, trades and OEMs
- Commissioning requirements written into the specifications and subcontracts
- Equipment list agreed, with the commissioning level each item must reach
- Submittals reviewed for testability, access and commissioning requirements
- Test scripts and acceptance criteria drafted for each level
L1: Factory acceptance testing (FAT)
- FAT procedures approved before the witness date
- Witness attendees confirmed for the owner, CxA and GC
- Nameplates and serial numbers match the approved submittals
- Tests completed to the approved procedure, with results recorded
- Deviations and punch items logged with an owner for each
- Release to ship signed once open items are closed or accepted
L2: Delivery, installation and pre-energization
- Receiving inspection done: shipping damage, tilt and shock indicators, quantities
- Equipment stored and protected to OEM requirements until installed
- Installed per the drawings and OEM instructions, with clearances and grounding verified
- Pre-functional checklists completed and signed by the installing trade
- Acceptance testing complete (for example insulation resistance and torque checks)
- Labels, arc flash labels and equipment IDs in place
- Deficiencies logged and closed before startup
L3: Energized startup
- Energization readiness confirmed and approved (see the energization checklist)
- OEM startup performed, with a signed startup report
- Protective settings applied and verified against the coordination study
- Operating values recorded: voltages, currents, temperatures and alarms
- Startup issues logged and resolved, warranty start dates recorded
L4: Functional performance testing
- Functional test scripts approved by the CxA
- Each system tested in every mode: normal, failure, transfer, alarm and recovery
- Controls, BMS and EPMS points verified end to end
- Failed tests corrected and retested, with results recorded
L5: Integrated systems testing (IST)
- IST plan, sequence and roles approved by the owner, GC and CxA
- Load banks, instrumentation, communications and safety plan in place
- Failure scenarios run across systems: utility loss, generator start, UPS and transfer, cooling failure
- Trend data captured and reviewed for each scenario
- Issues resolved or formally accepted by the owner before turnover
Turnover: owner acceptance
- O&M manuals, as-builts, warranties and spare parts delivered
- Operator training delivered and attendance recorded
- Commissioning issues log closed or accepted
- Final commissioning report and systems manual issued
- Owner acceptance signed
This checklist is a general guide. Always follow the approved commissioning plan, project specifications, OEM requirements, applicable codes and standards, and your site safety program. Also see the free Energization Readiness Checklist.